Q25E

Question

Preparing an operating budget—cost of goods sold budget 

Refer to the budgets prepared in Exercise E22-24. Determine the cost per kit to manufacture the model airplane kits. Grady projects sales of 100, 150, 100, and 200 kits for the next four quarters. Prepare a cost of goods sold budget for the year. Grady has no kits in beginning inventory. Round amounts to two decimal places.

Step-by-Step Solution

Verified
Answer

Answer


The total budgeted cost of goods sold is $3.025

1Step 1: Calculation of cost per unit

Amount ($)

Direct materials cost per kit (4 ounce per kit x $1/Ounce)

$4

Direct labor cost per kit (0.10 hour per kit x $10 per direct labor hour)

$1

Manufacturing overhead cost per kit (0.10 hour per kit x$5/DLHr)

$0.5

Total projected manufacturing cost per kit

$5.5


2Step 2: Preparation of cost of goods sold budget

Quarter 1

Quarter 2

Quarter 3

Quarter 4

Projected sales of kits

100

150

100

200

projected manufacturing cost per kit

$5.5

$5.5

$5.5

$5.5

Total budgeted cost of goods sold

$550

$825

$550

$1,100