Q20E

Question

Collins Company has the following data for the Assembly Department for August:

Unit in process at the beginning of august

900

Units started in august

2,000

Units completed and transferred

2,100

Units in process at the end of august

800

Conversion costs are added evenly throughout the process. The company uses the weighted-average method. Compute the equivalent units of production for direct materials and conversion costs for each independent scenario:

1. Units in process at the end of August are 20% complete; materials are added at the beginning of the process.

2. Units in process at the end of August are 80% complete; materials are added at the beginning of the process.

3. Units in process at the end of August are 20% complete; materials are added at the end of the process.

4. Units in process at the end of August are 80% complete; materials are added at the halfway point.

Step-by-Step Solution

Verified
Answer

Cases

EUP for direct material

EUP for conversion cost

  1. Units in process at the end of August are 20% complete; materials are added at the beginning of the process.

 

2,900

 

2,260

  1. Units in process at the end of August are 80% complete; materials are added at the beginning of the process.

 

2,900

 

 

2,740

  1. Units in process at the end of August are 20% complete; materials are added at the end of the process.

 

2,100

 

2,260

  1. Units in process at the end of August are 80% complete; materials are added at the halfway point.

 

2,900

 

 

2,740

1Step 1: Meaning of Manufacturing Process

The manufacturing process means the procedure undertaken by the manufacturing companies for converting the raw material into the finished goods by using the machinery, labor, etc. Manufacturing is integral to the economy.

2Step 2: Equivalent unit of production for direct materials when the unit in process at the end of August is 20%

EUP=Completedunits×Completion%+Inprocessunits×Completion%=2,100×100%+800×100%=2,900

3Step 3: Equivalent unit of production for conversion cost when the unit in process at the end of August is 20%

EUP=Completedunits×Completion%+Inprocessunits×Completion%=2,100×100%+800×20%=2,260

4Step 4: Equivalent unit of production for direct materials when the unit in process at the end of August is 80%

EUP=Completedunits×Completion%+Inprocessunits×Completion%=2,100×100%+800×100%=2,900

5Step 5: Equivalent unit of production for conversion cost when the unit in process at the end of August is 80%

EUP=Completedunits×Completion%+Inprocessunits×Completion%=2,100×100%+800×80%=2,740

6Step 6: Equivalent unit of production for direct materials when the unit in process at the end of August is 20%, and the materials are added at the end of the process.

EUP=Completedunits×Completion%+Inprocessunits×Completion%=2,100×100%+800×0%=2,100

7Step 7: Equivalent unit of production for conversion cost when the unit in process at the end of August is 20%,and the materials are added at the end of the process.

EUP=Completedunits×Completion%+Inprocessunits×Completion%=2,100×100%+800×20%=2,260

8Step 8: Equivalent unit of production for direct materials when the unit in process at the end of August is 80%, and the materials are added at the halfway point

EUP=Completedunits×Completion%+Inprocessunits×Completion%=2,100×100%+800×100%=2,900

9Step 9: Equivalent unit of production for conversion cost when the unit in process at the end of August is 80%,and the materials are added at the Halfway point

EUP=Completedunits×Completion%+Inprocessunits×Completion%=2,100×100%+800×80%=2,740