Rennie Plant Service completed a special landscaping job for Brenton Company. rennie uses ABC and has the following predetermined overhead allocation rates:

                  Activity                                                                   Predetermined

                                                  Allocation Base               Overhead Allocation Rate

                Designing               Number of designs                  \( 290 per design

                  Planting                Number of plants                     \) 20 per plant

 

The Rennie job included \(1,500 in plants; \)800 in direct labor; one design; and 30 plants.

 

Requirements

1. What is the total cost of the Brenton job?

Step-by-Step Solution

Verified
Answer

Total cost of Brenton job: $1,690

1Step-by-Step-Solution Step 1: Total overhead cost

Design cost=No. of designs×Predetermined over head allocation rate                     =1×$290                     =$290


Planting cost=No. of plants×Predetermined overhead allocation rate                      =30×$20                      =$600

Total overhead cost=Design cost+Planting cost                                =$290+$600                                =$890

2Step 2: Total cost of Brenton job

Total cost=Direct labor cost+Total overhead cost                 =$800+$890                 =$1,690