Q 36PGA-1

Question

Question: Blanchette Plant Service completed a special landscaping job for Kerry Company. Blanchette uses ABC and has the following predetermined overhead allocation rates:

                  Activity                                                                   Predetermined

                                                  Allocation Base               Overhead Allocation Rate

                Designing               Number of designs                  \( 290 per design

                  Planting                Number of plants                     \) 20 per plant

 

The Kerry job included \(750 in plants; \)1,300 in direct labor; one design; and 30 plants.

Requirements

1. What is the total cost of the Kerry job?

 

Step-by-Step Solution

Verified
Answer

Answer

Total cost of Kerry job: $2,190

 

1Step 1: Total overhead cost

Design cost =No. of designs × Predetermined allocation overhead rate                         = $1×$290                          = $290Planting cost =No. of plants × Predetermined allocation overhead rate                         = $30×$20                          = $600Total overhead cost =Design cost +Planning cost                                         =$290+$600                                          =$890

2Step 2: Total cost of Kerry job

Total  cost =Direct labour cost +Total overhead cost                                          =$1,300+$890                                          =$2,190