Problem 59
Question
Manufacturing Furniture A furniture factory makes wooden tables, chairs, and armoires. Each piece of furniture requires three operations: cutting the wood, assembling, and finishing. Each operation requires the number of hours ( \(h\) ) given in the table. The workers in the factory can provide 300 hours of cutting, 400 hours of assembling, and 590 hours of finishing each work week. How many tables, chairs, and armoires should be produced so that all available labor-hours are used? Or is this impossible? $$\begin{array}{|l|c|c|c|} \hline & \text { Table } & \text { Chair } & \text { Armoire } \\ \hline \text { Cutting (h) } & \frac{1}{2} & 1 & 1 \\ \text { Assembling (h) } & \frac{1}{2} & 1 \frac{1}{2} & 1 \\ \text { Finishing (h) } & 1 & 1 \frac{1}{2} & 2 \\ \hline \end{array}$$
Step-by-Step Solution
VerifiedKey Concepts
Constraints Optimization
To tackle such problems, one needs to set up a system that balances all constraints.
- For cutting: Total time is limited to 300 hours.
- For assembling: Total time is limited to 400 hours.
- For finishing: Total time is limited to 590 hours.
Labor-Hour Calculations
For instance:
- Tables require \(\frac{1}{2}\) hour for cutting, \(\frac{1}{2}\) hour for assembling, and 1 hour for finishing.
- Chairs need 1 hour for cutting, \(1\frac{1}{2}\) hours for assembling, and \(1\frac{1}{2}\) hours for finishing.
- Armoires demand 1 hour for cutting, 1 hour for assembling, and 2 hours for finishing.
System of Equations
Given our constraints, the system of equations is represented by:
- \( \frac{1}{2}x + y + z = 300 \) for cutting
- \( \frac{1}{2}x + \frac{3}{2}y + z = 400 \) for assembling
- \( x + \frac{3}{2}y + 2z = 590 \) for finishing
In the step-by-step solution, errors can occur during calculations, so careful evaluation and verification of each step is essential to ensure consistency and correctness of the derived solutions.