Problem 45
Question
In Example \(1,\) one crew could drywall a house in 4 days, and another crew could drywall the same house in 5 days. We were asked to find how long it would take them to drywall the house working together. Explain why each of the following approaches is incorrect. The time it would take to drywall the house: is the sum of the lengths of time it takes each crew to drywall the house: 4 days \(+5\) days \(=9\) days. drywall the house: 4 days \(+5\) days \(=9\) days. is the difference in lengths of time it takes each crew to drywall the house: 5 days \(-4\) days \(=1\) day. is the average of the lengths of time it takes each crew to drywall the house: \(\frac{4 \text { days }+5 \text { days }}{2}=\frac{9}{2}\) days \(=4 \frac{1}{2}\) days.
Step-by-Step Solution
VerifiedKey Concepts
Understanding Rate of Work in Combined Tasks
For instance, if one crew can drywall a house in 4 days, their rate of work is \(\frac{1}{4}\) of the house per day. If the second crew takes 5 days, their rate is \(\frac{1}{5}\) of the house per day. Working together, these rates add up. This means they collectively complete \(\frac{1}{4} + \frac{1}{5} = \frac{5+4}{20} = \frac{9}{20}\) of the house per day.
- Identify each crew's rate: Crew 1 is \(\frac{1}{4}\), Crew 2 is \(\frac{1}{5}\).
- Add the rates together: \(\frac{1}{4} + \frac{1}{5}\).
- Find the combined rate: \(\frac{9}{20}\) of a house per day.
Recognizing Incorrect Approaches in Combined Work
Addition of Individual Times: Some might think adding the times from each crew gives the time needed together (4 days \(+ 5\) days = 9 days). This method mistakenly implies the crews slow each other down. Actually, working together should be faster, not slower.
Subtraction of Times: Another incorrect approach is subtracting the times (5 days \(- 4\) days = 1 day). This method incorrectly assumes that the faster crew will magically speed up the entire process. Realistically, both contribute to finishing the drywalling together, not as a race.
Average of Times: Calculating the average \(\frac{4 \,\text{days} + 5 \,\text{days}}{2} = 4.5\) days might seem logical since averages provide a kind of "middle" value. However, it fails in combined work problems because combining efforts usually results in less time than even the fastest individual takes. Always rely on the sum of rates rather than simplistic arithmetic operations for these problems.
Accurately Calculating Time in Collaborative Tasks
Begin with the combined rate, which we calculated as \(\frac{9}{20}\) of the house per day. This means each day, they jointly finish \(\frac{9}{20}\) of the drywalling task.
To find out how many days are required for the whole task, you use the formula:\[\text{Time} = \frac{\text{Total Task}}{\text{Combined Rate of Work}}\]Since the total task is the entire house, represented by 1 unit, here's how you calculate:\[\text{Time} = \frac{1}{\frac{9}{20}} = \frac{20}{9} \approx 2.22 \,\text{days}\]This calculation tells us the time both crews will take together. It neatly ties into the idea that combining efforts reduces time. While doing this, remember to focus on total units produced or finished per day. This approach allows for an accurate calculation of the day's number required, facilitating better planning and organization of collaborative work.