Problem 14
Question
Typing Project One person can complete a typing project in 6 hours, and another can complete the same project in 8 hours. How long will it take the two people working together to complete the project?
Step-by-Step Solution
Verified Answer
It will take approximately 3.43 hours for the two people working together to complete the project.
1Step 1: Identify the individual work rates
First, identify the rate at which each person can complete the work individually. The rate is defined as the amount of work that can be done per unit time. Here, the first person completes the project in 6 hours, thus their rate is \(1/6\) project per hour. Similarly, the second person completes the project in 8 hours, so their rate is \(1/8\) project per hour.
2Step 2: Calculate combined work rate
The total rate of the two people working together is the sum of their individual rates. Hence, the combined work rate is \((1/6 + 1/8)\) projects per hour.
3Step 3: Find the time taken to complete the project
To find the time taken to complete the project, divide the total work (one project) by their combined work rate. That is \(1 / (1/6 + 1/8)\) hours.
Key Concepts
Individual Work RateCombined Work RateTime Taken to Complete Work
Individual Work Rate
When we speak about 'individual work rate,' we're looking at how much work a single person can do in a certain time period. For the given problem, it's all about how quickly each of our two people can complete a typing project on their own.
This is expressed as a fraction, representing the part of the work done in one hour.
This is expressed as a fraction, representing the part of the work done in one hour.
- For the first person, completing the project in 6 hours means they do \( \frac{1}{6} \) of the project per hour.
- For the second person, completing it in 8 hours gives them a rate of \( \frac{1}{8} \) of the project per hour.
Combined Work Rate
Once we know each person's individual work rate, the next step is to find out how fast they can complete the project together, which is their 'combined work rate.'
In this context, the combined work rate is simply the sum of the individual work rates.
For our typists:
In this context, the combined work rate is simply the sum of the individual work rates.
For our typists:
- Their combined rate is \( \frac{1}{6} + \frac{1}{8} \) of the project per hour.
- This requires us to calculate \( \frac{1}{6} + \frac{1}{8} \), which involves finding a common denominator to add these fractions.
- Once we have a common denominator, we can add these fractions to find their combined rate in projects per hour.
Time Taken to Complete Work
The final piece of the puzzle in work rate problems is determining the total time required to finish the job when working together—this is the 'time taken to complete work.'
We find this by diving into a simple division operation: taking the whole project (considered as 1 unit of work) and dividing it by the combined work rate.
We find this by diving into a simple division operation: taking the whole project (considered as 1 unit of work) and dividing it by the combined work rate.
- The formula here is \( \text{Time} = \frac{1}{\text{Combined Work Rate}} \).
- For example, with the combined rate from our earlier step, \( \frac{1}{6} + \frac{1}{8} \), the time it takes is \( \frac{1}{(\frac{1}{6} + \frac{1}{8})} \).
- After calculating the combined rate, we substitute this into the formula to find the total time they need.
Other exercises in this chapter
Problem 13
Justify each step of the solution. $$ \begin{aligned} 5 x+15 &=0 \\ 5 x+15-15 &=0-15 \\ 5 x &=-15 \\ \frac{5 x}{5} &=\frac{-15}{5} \\ x &=-3 \end{aligned} $$
View solution Problem 14
Determine whether each value of \(x\) is a solution of the inequality. \(\frac{2}{3} x+4
View solution Problem 14
Find a ratio that compares the relative sizes of the quantities. (Use the same units of measurement for both quantities.) 81 feet to 27 feet
View solution Problem 14
Convert the percent to a decimal. $$0.3 \%$$
View solution